Sunday 25 November 2018

Narrowboat fitout - end November update

Well, it's been a rather slow, tedious few weeks.
I really need to get the inverter connected up, so I can run some decent power tools. I also need to get some charge into the two sets of batteries.
But, before I can connect up the inverter, I need a bulkhead to hang it on.
Before I can build the bulkhead, I need to fix the ceiling battens, so I have something to fix to.
Before I can fix the ceiling battens, I need to complete the second layer of insulation...
I also need to inject every gap between the pieces of Celotex with expanding foam, which makes a godawful mess and takes 24 hours to cure fully, so the cutting back process can't be rushed.

I've almost completed the insulation in the engine room and back cabin. This has been complicated by the fact that everything is either curved, angled or both, so every piece has to be custom-fit.

That all pretty well sums up the state of play - a whole bunch of things that are dependent on something else happening. So I've just knuckled down to the (now very tedious) job of fitting all the 12mm Celotex to the ceiling and squirting expanding foam into any gaps.


Next will be the job of applying foil tape to all the joins between the Celotex panels on the ceiling and port side. Although this is another very tedious job, it's vital, as it prevents moisture migrating through to cold steel below.

I don't deny, I will be glad to get this stage finished. Getting the pile of Celotex off the floor and onto the walls/ceilings has helped to make more room.

Hopefully, the next post will be more interesting!

Sunday 11 November 2018

First month - insulating my narrowboat


Time flies, so they say... I've just realised it's been a month since the last post!

Once Calbourne was safely in the water, it was time to take stock a bit. The departure from XR&D had been chaotic, to say the least. All the tools and materials, which had been conveniently stacked outside the boat in the DIY shed, had been more or less thrown into the boat while the crane and lorry were waiting!

So it was a case of sorting things out and trying to store them where they would cause the minimum of obstruction to the next jobs. Easier said than done, but the space in the forecabin was very welcome. The bulkiest material was the 50mm Celotex, so it became a priority to get this insulation onto the walls. 

Not much room to move!
When floated, the boat was already sitting with the stern higher than I would have liked, so I decided to complete the filler pipe and breather for the water tank and do a test fill. I needed to see the effect of a full tank. I had a flow gauge, so I connected it up and turned the tap on. And waited... for nearly two hours. Finally, with 923L showing on the gauge, water came out of the overflow. The bow was now 3" lower and the boat had listed quite a bit to port. Clearly, I needed to shift a lot of ballast toward the stern and to starboard. This was made more difficult, as the cooker was bridging two of the plywood floor panels, but I moved what I could access. 



Fitting the Celotex was fairly straightforward - cut and then fix in place with spray glue. But first, all the battens needed to fixed. Most of these were cut to size in the workshop to save time. After fitting the panels, the gaps behind the steel angles were filled with expanding foam. Once set, it was trimmed back and all joins were covered with foil tape, to provide a continuous vapour barrier. 



Because the cooker was hard up against the port side, it was logical to concentrate on the starboard side. I was keen to see how the 'underfloor' heating pipes would sit in the hull sides, so I pressed on with fitting the horizontal battens. These had to be carefully spaced, to make sure they would accommodate the six pipe runs and the cabling conduit above. A first attempt at fitting the panels revealed an issue - the need to allow room for the pipes to sweep round at the end of each run. This involved some adjustment to the cutting of the polystyrene panels, but I soon had the first two installed. These will be permanently fixed in place with PVA adhesive.

Spot the problem?

A 40mm x 25mm plastic conduit was fitted above the top batten, which left a gap to allow for a section of 30mm Celotex to insulate the bottom of the gunwale.

I then pressed on with getting the port cabin side insulated. With the weather getting colder, I was keen to make my floating steel box a bit cosier! While doing this, I allowed for a channel, to allow the combustion air for the cooker to be drawn up from the bilge.

Next, I started on the ceiling insulation. I found that Celotex is not very bendy, so instead of fitting 25mm as planned, I would have to fit two layers of 12mm, to allow it to follow the curve of the roof. This was quite straightforward, just a bit repetitive!



In between doing the insulation, ProCast finally turned up with the remaining chimney collars and hatch. This was quite a relief, as I'd had to glue pieces of plywood over the holes to keep the weather out.
The hatch is very heavy!
They also brought the porthole liners. It was a relief to see that they fitted neatly into the holes I'd cut in the insulation. They are made of glass fibre, but look remarkably like wood - and should solve the perennial rotting problem.



Although the marina has the benefit of mains hook-up, the supply is limited to 6 Amps. This means that even modest hand-held tools, like a circular saw, kick out the breaker. In order to use more powerful tools, I need to get the inverter connected up.


Outside, Calbourne is going a bright orange colour as she starts to rust. This is causing a few raised eyebrows and more than a few questions! The reason for this is simple. The boat will be grit blasted and painted next Spring. The grit blaster has told me that the millscale will come off the steel better if it's allowed to rust first. Needless to say, I'm looking forward to seeing her looking more respectable!

Maiden voyage and cooker!

It's been an eventful few days! We've been enjoying a spell of unseasonably warm weather, which was predicted to end on the last day...